Grid GuardianOpen the evidence in the app

Waterbeach Landfil Site

Waterbeach Landfil Site, Amey, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3.2 MW, grid supply point Burwell.

Customer
Amey
Status
Connected
Capacity
3.2 MW
Maximum import capacity
0 MW
Technology
Bioenergy (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Burwell
Bulk supply point
Histon Grid 33kV
Point of connection
Landbeach Primary 11kV
Voltage
11 kV
Date connected
30 Apr 2008
In a connection queue
No
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Waterbeach
Postcode
CB25 9PG

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source