Grid GuardianOpen the evidence in the app

Walton Water Treatment Works

Walton Water Treatment Works, Affinity Water Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.2 MW, grid supply point West Weybridge.

Customer
Affinity Water Limited
Status
Connected
Capacity
1.2 MW
Technology
Fossil - Oil (Other)
Flexible connection
No
Grid supply point
West Weybridge
Bulk supply point
West Weybridge Grid 33kV
Point of connection
Walton 11kV
Voltage
11 kV
Date connected
27 Mar 2013
In a connection queue
No
Row last updated by the DNO
12 Jul 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Walton Lane, Walton-On-Thames
Postcode
KT12 1QP
Export MPAN
1900090934948
Import MPAN
1900020430212

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source