Wadlow Windfarm (West Connection - BB1)

Wadlow Windfarm (West Connection - BB1), Wadlow Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 14.2 MW, grid supply point Burwell.

Customer
Wadlow Energy Limited
Status
Connected
Capacity
14.2 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Burwell
Bulk supply point
Fulbourn Grid 33kV
Voltage
33 kV
Date connected
13 Sept 2012
In a connection queue
No
Row last updated by the DNO
14 Dec 2020
Licence area
EPN
Address
Cambridge
Postcode
CB21 5BF
Export MPAN
1030078017157

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.