Tilbury Docks Ph2
Tilbury Docks Ph2, Thameside Energy Recovery Facility Limited 2021, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 40 MW, grid supply point Tilbury.
- Customer
- Thameside Energy Recovery Facility Limited 2021
- Status
- Accepted to connect
- Capacity
- 40 MW
- Technology
- Energy from waste (Steam turbine (thermal power plant))
- Flexible connection
- No
- Grid supply point
- Tilbury
- Voltage
- 132 kV
- Date accepted
- 22 Aug 2017
- Target energisation
- 30 Oct 2025
- In a connection queue
- Yes
- Row last updated by the DNO
- 13 Sept 2024
- Licence area
- EPN
- Address
- Tilbury
- Postcode
- RM18 7NU
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.