Grid GuardianOpen the evidence in the app

The Old Grain Store

The Old Grain Store, Chaldean Estate Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.5 MW, grid supply point Rye House.

Customer
Chaldean Estate Limited
Status
Accepted to connect
Capacity
2.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Rye House
Bulk supply point
Rye House Grid 33kV
Point of connection
Much Hadham Primary 11kV
Voltage
132 kV
Date accepted
24 Jul 2015
Target energisation
31 Dec 2024
In a connection queue
Yes
Row last updated by the DNO
13 Oct 2023
Licence area
EPN
Address
Bromley Lane, Much Hadham
Postcode
SG10 6HU

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source