Temporis WF Eye Airfield
Temporis WF Eye Airfield, The Natural Power Consultants Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 6.8 MW, grid supply point Bramford.
- Customer
- The Natural Power Consultants Limited
- Status
- Connected
- Capacity
- 6.8 MW
- Maximum import capacity
- 0.1 MW
- Technology
- Onshore wind (Onshore wind turbines)
- Flexible connection
- No
- Grid supply point
- Bramford
- Bulk supply point
- Diss Grid 33kV
- Voltage
- 33 kV
- Date connected
- 17 Oct 2013
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- EPN
- Address
- Eye
- Postcode
- IP23 8BW
- Export MPAN
- 1030085020190
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.