Stort Solar Farm

Stort Solar Farm, Low Carbon Solar Park 18 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 35 MW, grid supply point Rye House.

Customer
Low Carbon Solar Park 18 Limited
Status
Accepted to connect
Capacity
35 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Rye House
Bulk supply point
Harlow West Grid 33kV
Voltage
33 kV
Date accepted
30 Jun 2021
Target energisation
31 Oct 2031
In a connection queue
Yes
Row last updated by the DNO
16 Jan 2023
Licence area
EPN
Address
Roydon
Postcode
CM19 5HE

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source