Grid GuardianOpen the evidence in the app

Stanton Hatchery

Stanton Hatchery, York Green Renewables Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1 MW, grid supply point Bramford.

Customer
York Green Renewables Limited
Status
Connected
Capacity
1 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Thetford Grid 33kV
Point of connection
Stanton Primary 11kV
Voltage
11 kV
Date connected
18 Nov 2013
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Grove Lane, Bury St Edmunds
Postcode
IP31 2BB
Export MPAN
1050000529502

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source