Grid GuardianOpen the evidence in the app

Spring Way

Spring Way, Energetics Electricity, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Elstree.

Customer
Energetics Electricity
Status
Connected
Capacity
30 MW
Technology
Gas (Other)
Flexible connection
No
Grid supply point
Elstree
Bulk supply point
Piccotts End Grid 33kV
Voltage
33 kV
Date connected
1 Oct 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Hemel Hempstead
Postcode
HP2 7SU
Export MPAN
1099000011462

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source