Speedgate Farm

Speedgate Farm, Chimmens Energy Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Northfleet East.

Customer
Chimmens Energy Limited
Status
Accepted to connect
Capacity
49.9 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Northfleet East
Voltage
132 kV
Date accepted
27 May 2022
Target energisation
31 Oct 2037
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Speedgate Farm, Longfield
Postcode
DA3 8NJ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.