Sewage Treatment Works - Phs Ii

Sewage Treatment Works - Phs Ii, Anglian Water, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.4 MW, grid supply point Bramford.

Customer
Anglian Water
Status
Connected
Capacity
2.4 MW
Maximum import capacity
1.2 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Cliff Quay Grid 33kV
Point of connection
Fore Hamlet Primary 11kV
Voltage
11 kV
Date connected
18 Mar 2011
In a connection queue
No
Row last updated by the DNO
15 Jan 2021
Licence area
EPN
Address
Ipswich
Postcode
IP3 0ET
Export MPAN
1030073208772

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.