Riverside Energy Park
Riverside Energy Park, Cory Riverside Energy, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 88.6 MW, grid supply point Littlebrook 132kV (LPN).
- Customer
- Cory Riverside Energy
- Status
- Accepted to connect
- Capacity
- 88.6 MW
- Technology
- Energy from waste, Storage (Steam turbine (thermal power plant))
- Flexible connection
- No
- Grid supply point
- Littlebrook 132kV (LPN)
- Voltage
- 132 kV
- Date accepted
- 14 Feb 2022
- Target energisation
- 14 Apr 2026
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Nov 2024
- Licence area
- London Power Networks plc
- Address
- Norman Road, Belvedere
- Postcode
- DA17 6JY
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.