Potters Bar Solar Farm

Potters Bar Solar Farm, UK Sustainable Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.5 MW, grid supply point Elstree.

Customer
UK Sustainable Energy Limited
Status
Connected
Capacity
4.5 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Elstree
Bulk supply point
Hatfield Grid 33kV
Point of connection
West Potters Bar Primary 11kV
Voltage
11 kV
Date connected
31 Mar 2017
In a connection queue
No
Row last updated by the DNO
14 Feb 2024
Licence area
EPN
Address
Cranborne Road, Potters Bar
Postcode
EN6 3JR
Export MPAN
1050001299965

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source