Port Of Tilbury Wind Farm

Port Of Tilbury Wind Farm, Port of Tilbury London, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 9.2 MW, grid supply point Tilbury.

Customer
Port of Tilbury London
Status
Connected
Capacity
9.2 MW
Maximum import capacity
28 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Tilbury
Bulk supply point
Tilbury Compact Grid 33kV
Voltage
33 kV
Date connected
1 Feb 2013
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Tilbury
Postcode
RM18 7EH
Export MPAN
1030084129409

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.