NFPA

NFPA, Viridor Waste Management Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 7 MW, grid supply point Canterbury.

Customer
Viridor Waste Management Limited
Status
Connected
Capacity
7 MW
Technology
Bioenergy (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Canterbury
Bulk supply point
Canterbury South 33kV
Voltage
33 kV
Date connected
9 Jan 1997
In a connection queue
No
Row last updated by the DNO
15 Jan 2021
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Shelford Landfill 8147, Canterbury
Postcode
CT2 0PR
Export MPAN
1900060866082

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.