Napoleon Solar Farm

Napoleon Solar Farm, Low Carbon UK Solar Investment Company Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Northfleet East.

Customer
Low Carbon UK Solar Investment Company Limited
Status
Accepted to connect
Capacity
20 MW
Technology
Solar, Storage (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Northfleet East
Bulk supply point
Pembury Grid 33kV
Voltage
33 kV
Date accepted
2 Nov 2021
Target energisation
10 Jan 2027
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Tonbridge
Postcode
TN12 6SS

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.