Grid GuardianOpen the evidence in the app

Mucking Power Station

Mucking Power Station, EDL UK Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 7.89 MW, grid supply point Tilbury.

Customer
EDL UK Limited
Status
Connected
Capacity
7.89 MW
Maximum import capacity
0.3 MW
Technology
Bioenergy (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Tilbury
Bulk supply point
Tilbury
Voltage
11 kV
Date connected
3 Jul 2000
In a connection queue
No
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Mucking Wharf Road, Stanford-Le-Hope
Postcode
SS17 0RN
Export MPAN
1023470462707
Import MPAN
1014570507369

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source