Grid GuardianOpen the evidence in the app

Monkton Court Farm

Monkton Court Farm, Brightside Connections Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Richborough.

Customer
Brightside Connections Limited
Status
Accepted to connect
Capacity
49.9 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Richborough
Voltage
132 kV
Date accepted
5 Jun 2025
In a connection queue
Yes
Row last updated by the DNO
13 Jun 2025
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Monkton Street, Ramsgate
Postcode
CT3 1JB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source