Grid GuardianOpen the evidence in the app

Medway Enterprise Centre

Medway Enterprise Centre, Reliance Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Kingsnorth.

Customer
Reliance Energy Limited
Status
Connected
Capacity
20 MW
Technology
Fossil - Oil (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Kingsnorth
Point of connection
Strood 11kV
Voltage
11 kV
In a connection queue
No
Row last updated by the DNO
12 Jul 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Enterprise Close, Rochester
Postcode
ME2 4SY
Export MPAN
1900092463638/1900092463860

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source