Grid GuardianOpen the evidence in the app

Manor Farm

Manor Farm, Harmony BD Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 11.58 MW, grid supply point Northfleet East.

Customer
Harmony BD Limited
Status
Connected
Capacity
11.58 MW
Maximum import capacity
11 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Northfleet East
Bulk supply point
Northfleet East 33kV
Voltage
33 kV
Date connected
27 Feb 2023
In a connection queue
No
Row last updated by the DNO
15 Jan 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
New Barn Road, Gravesend
Postcode
DA13 9PU
Export MPAN
1997000000175
Import MPAN
1997000000166

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source