Lye Green Solar Farm

Lye Green Solar Farm, Exagen Development Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 50 MW, grid supply point Elstree.

Customer
Exagen Development Limited
Status
Accepted to connect
Capacity
50 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Elstree
Voltage
132 kV
Date accepted
10 Mar 2022
Target energisation
31 Oct 2033
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
St Albans
Postcode
AL2 3NN

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.