Lnd Sacketts Hill Farm
Lnd Sacketts Hill Farm, GF Thanet Energy Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 22.45 MW, grid supply point Richborough.
- Customer
- GF Thanet Energy Limited
- Status
- Accepted to connect
- Capacity
- 22.45 MW
- Technology
- Storage (Storage - Electrochemical (Batteries))
- Flexible connection
- Yes (capacity not firm)
- Grid supply point
- Richborough
- Bulk supply point
- Thanet Grid
- Point of connection
- Thanet Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 2 Sept 2023
- Target energisation
- 20 Nov 2036
- In a connection queue
- Yes
- Row last updated by the DNO
- 15 Apr 2024
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Land Adj Sacketts Hill Farm, Broadstairs
- Postcode
- CT10 2QS
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.