Grid GuardianOpen the evidence in the app

Lebanon Farm

Lebanon Farm, Cedar Utility Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 40 MW, grid supply point Tilbury.

Customer
Cedar Utility Limited
Status
Accepted to connect
Capacity
40 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Tilbury
Voltage
132 kV
Date accepted
14 Oct 2021
Target energisation
30 Oct 2030
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2024
Licence area
EPN
Address
Lower Dunton Road, Upminster
Postcode
RM14 3JD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source