Grid GuardianOpen the evidence in the app

Land Part Of Swan Lane Pier

Land Part Of Swan Lane Pier, Disco Powered Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.5 MW, grid supply point City Road.

Customer
Disco Powered Limited
Status
Accepted to connect
Capacity
1.5 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
City Road
Bulk supply point
Bankside C 11kV
Voltage
11 kV
Date accepted
28 May 2021
In a connection queue
Yes
Row last updated by the DNO
14 Feb 2025
Licence area
London Power Networks plc
Address
City Of London
Postcode
EC4R 3AF

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source