Kingsnorth Works 324531

Kingsnorth Works 324531, Ashford Power Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 21 MW, grid supply point Kingsnorth.

Customer
Ashford Power Limited
Status
Connected
Capacity
21 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Kingsnorth
Point of connection
Kingsnorth Grid 11kV
Voltage
11 kV
Date connected
21 Sept 2017
In a connection queue
No
Row last updated by the DNO
12 Feb 2021
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Kingsnorth Industrial Estate, Rochester
Postcode
ME3 9NZ
Export MPAN
1900091577219

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.