Kingsnorth Power Station

Kingsnorth Power Station, Medway Energy Recovery Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Kingsnorth.

Customer
Medway Energy Recovery Limited
Status
Accepted to connect
Capacity
49.9 MW
Technology
Energy from waste (Steam turbine (thermal power plant))
Flexible connection
No
Grid supply point
Kingsnorth
Point of connection
Kingsnorth Grid 132kV
Voltage
132 kV
Date accepted
18 Jun 2021
Target energisation
31 Dec 2024
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Kingsnorth Power Station, Rochester
Postcode
ME3 9NQ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.