Kingsey Solar Farm
Kingsey Solar Farm, Callie's Solar Farm Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Amersham.
- Customer
- Callie's Solar Farm Limited
- Status
- Accepted to connect
- Capacity
- 30 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- Amersham
- Bulk supply point
- Ilmer Grid 33kV
- Voltage
- 33 kV
- Date accepted
- 11 Oct 2020
- Target energisation
- 31 Dec 2024
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Aug 2023
- Licence area
- EPN
- Address
- Ilmer
- Postcode
- HP27 9QX
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.