Ingham Solar Farm

Ingham Solar Farm, Solarfields Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Bramford.

Customer
Solarfields Limited
Status
Connected
Capacity
20 MW
Maximum import capacity
0.05 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Thetford Grid 33kV
Voltage
33 kV
Date connected
2 Aug 2022
In a connection queue
No
Row last updated by the DNO
14 Sept 2022
Licence area
EPN
Address
Suffolk, Bury St Edmunds
Postcode
IP31 1NQ
Export MPAN
1050002077463
Import MPAN
1050002077454

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.