Handley Page B
Handley Page B, AMP Energy Services, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4 MW, grid supply point Elstree.
- Customer
- AMP Energy Services
- Status
- Connected
- Capacity
- 4 MW
- Technology
- Gas (Gas turbine (OCGT))
- Flexible connection
- No
- Grid supply point
- Elstree
- Bulk supply point
- Hatfield Grid 33kV
- Point of connection
- Shenley Primary 11kV
- Voltage
- 11 kV
- Date connected
- 28 Sept 2020, 28 Sept 2020
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- EPN
- Address
- Old Parkbury Lane, St Albans
- Postcode
- AL2 2DZ
- Export MPAN
- 1050002001349, 1050002001376
- Import MPAN
- 1050002001330
Register rows
| Row | Status | MW | Target |
|---|---|---|---|
| 1 | Connected | 4 | |
| 2 | Connected | 2 |
Rows at one site are not summed.
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.