Greatness Quarry Landfill 451338
Greatness Quarry Landfill 451338, Cory Environmental, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.2 MW, grid supply point Northfleet East.
- Customer
- Cory Environmental
- Status
- Connected
- Capacity
- 2.2 MW
- Technology
- Bioenergy (Gas turbine (OCGT))
- Flexible connection
- No
- Grid supply point
- Northfleet East
- Bulk supply point
- Chelsfield Grid 33kV
- Point of connection
- North Sevenoaks 11kV
- Voltage
- 11 kV
- Date connected
- 26 Jan 2011
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Bat And Ball Road, Sevenoaks
- Postcode
- TN14 5BP
- Export MPAN
- 1900090580239
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.