Grid GuardianOpen the evidence in the app

Former Airfield

Former Airfield, Ventus VCT PLC, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 10 MW, grid supply point Bramford.

Customer
Ventus VCT PLC
Status
Connected
Capacity
10 MW
Maximum import capacity
0.25 MW
Technology
Onshore wind (Onshore wind turbines)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Halesworth Grid 33kV
Voltage
33 kV
Date connected
12 Aug 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Upper Holton, Halesworth
Postcode
IP19 8NH
Export MPAN
1050000769127

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source