Fenland Farm

Fenland Farm, Strategic Energy Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Burwell.

Customer
Strategic Energy Limited
Status
Connected
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Burwell
Bulk supply point
Histon Grid 33kV
Voltage
33 kV
Date connected
1 Apr 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
EPN
Address
Stretham, Ely
Postcode
CB6 3LF
Export MPAN
1050000774172

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.