Eye Power Station

Eye Power Station, EPR Eye Power Station, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 17 MW, grid supply point Bramford.

Customer
EPR Eye Power Station
Status
Connected
Capacity
17 MW
Maximum import capacity
1 MW
Technology
Energy from waste (Other)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Diss Grid 33kV
Voltage
33 kV
Date connected
12 Feb 1999
In a connection queue
No
Row last updated by the DNO
14 Dec 2020
Licence area
EPN
Address
Oaksmere Business Park, Eye
Postcode
IP23 7DH
Export MPAN
1023479132320

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.