Grid GuardianOpen the evidence in the app

Emirates Stadium

Emirates Stadium, Impact Power Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.8 MW, grid supply point Islington.

Customer
Impact Power Limited
Status
Connected
Capacity
2.8 MW
Maximum import capacity
0 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Islington
Point of connection
Holloway 11kV
Voltage
11 kV
Date connected
21 Nov 2018
In a connection queue
No
Row last updated by the DNO
14 Dec 2021
Licence area
London Power Networks plc
Address
Emirates Stadium, Hornsey
Postcode
N7 7AJ
Export MPAN
1200062401665

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source