Elmer WTW 174946, Sutton and East Surrey Water plc, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3.4 MW, grid supply point West Weybridge.
- Customer
- Sutton and East Surrey Water plc
- Status
- Connected
- Capacity
- 3.4 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- West Weybridge
- Bulk supply point
- Leatherhead Grid 33kV
- Point of connection
- Leatherhead Town 11kV
- Voltage
- 11 kV
- Date connected
- 31 Mar 2016
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
- Address
- Hawks Hill, Leatherhead
- Postcode
- KT22 9DA
- Export MPAN
- 1900091380291
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.