Grid GuardianOpen the evidence in the app

Dennington Hall Farm

Dennington Hall Farm, Grupotec Solar UK 10 Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 20 MW, grid supply point Bramford.

Customer
Grupotec Solar UK 10 Limited
Status
Accepted to connect
Capacity
20 MW
Technology
Solar (Photovoltaic)
Flexible connection
Yes (capacity not firm)
Grid supply point
Bramford
Voltage
33 kV
Date accepted
22 Jun 2026
In a connection queue
Yes
Row last updated by the DNO
14 Jul 2026
Licence area
EPN
Address
Bruisyard Country Estate, Saxmundham
Postcode
IP17 2EJ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source