Denham Way
Denham Way, Thames Water Utilities Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.5 MW, grid supply point Watford South.
- Customer
- Thames Water Utilities Limited
- Status
- Accepted to connect
- Capacity
- 2.5 MW
- Technology
- Bioenergy (Engine (combustion / reciprocating))
- Flexible connection
- No
- Grid supply point
- Watford South
- Bulk supply point
- Rickmansworth Grid 132 & 33/11KV
- Voltage
- 11 kV
- Date accepted
- 1 Oct 2025
- In a connection queue
- Yes
- Row last updated by the DNO
- 14 Feb 2025
- Licence area
- EPN
- Address
- Maples Cross, Rickmansworth
- Postcode
- WD3 9SQ
- Export MPAN
- 1023478111817
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.