Chediston Hall
Chediston Hall, Solar Century Holdings Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12.48 MW, grid supply point Bramford.
- Customer
- Solar Century Holdings Limited
- Status
- Connected
- Capacity
- 12.48 MW
- Maximum import capacity
- 0.1 MW
- Technology
- Solar (Photovoltaic)
- Flexible connection
- No
- Grid supply point
- Bramford
- Bulk supply point
- Halesworth Grid 33kV
- Voltage
- 33 kV
- Date connected
- 28 Mar 2013
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- EPN
- Address
- Halesworth, Bramford
- Postcode
- IP19 0AD
- Export MPAN
- 1030083806256
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.