Chase Fm Hospital Enfield

Chase Fm Hospital Enfield, WSP | Parsons Brinckerhoff, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.2 MW, grid supply point Tottenham.

Customer
WSP | Parsons Brinckerhoff
Status
Connected
Capacity
4.2 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Tottenham
Bulk supply point
Palmers Green Grid 33kV
Point of connection
North Enfield Primary 11kV
Voltage
11 kV
Date connected
12 Apr 2018
In a connection queue
No
Row last updated by the DNO
14 Nov 2024
Licence area
EPN
Address
127 Ridgeway, Enfield
Postcode
EN2 8JL
Export MPAN
1050001708747

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.