Chalk Lane Snetterton Norwich

Chalk Lane Snetterton Norwich, BWSC East Anglia Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 3 MW, grid supply point Bramford.

Customer
BWSC East Anglia Limited
Status
Connected
Capacity
3 MW
Maximum import capacity
0 MW
Technology
Bioenergy (Steam-gas turbine (CCGT))
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Diss Grid 33kV
Voltage
33 kV
Date connected
1 Feb 2018
In a connection queue
No
Row last updated by the DNO
14 Mar 2024
Licence area
EPN
Address
Chalk Lane, Norwich
Postcode
NR16 2JZ

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.