Cattlegate Farm
Cattlegate Farm, D Williams & Co, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.5 MW, grid supply point Tottenham.
- Customer
- D Williams & Co
- Status
- Connected
- Capacity
- 1.5 MW
- Technology
- Bioenergy (Steam-gas turbine (CCGT))
- Flexible connection
- No
- Grid supply point
- Tottenham
- Bulk supply point
- Palmers Green Grid 33kV
- Point of connection
- North Enfield Primary 11kV
- Voltage
- 11 kV
- Date connected
- 1 Feb 2016
- In a connection queue
- No
- Row last updated by the DNO
- 13 Nov 2020
- Licence area
- EPN
- Address
- Enfield
- Postcode
- EN2 8UB
- Export MPAN
- 1050000769925
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.