Capel Grange Solar Farm

Capel Grange Solar Farm, West Coast Energy, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 4.08 MW, grid supply point Northfleet East.

Customer
West Coast Energy
Status
Connected
Capacity
4.08 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Northfleet East
Bulk supply point
Pembury Grid 33kV
Voltage
33 kV
Date connected
21 Mar 2016
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Badsell Road, Tonbridge
Postcode
TN12 6QX
Export MPAN
1900091353303

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.