Grid GuardianOpen the evidence in the app

Bywaters

Bywaters, Bywaters, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1 MW, grid supply point West Ham.

Customer
Bywaters
Status
Connected
Capacity
1 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
West Ham
Point of connection
West Ham Grid 11kV
Voltage
11 kV
Date connected
22 Dec 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
London Power Networks plc
Address
Twelvetrees Crescent, Bow
Postcode
E3 3JG
Export MPAN
1200061837995

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source