Bullen Lane

Bullen Lane, Care Power (Bramford) Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.99 MW, grid supply point Bramford.

Customer
Care Power (Bramford) Limited
Status
Accepted to connect
Capacity
49.99 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Bramford
Voltage
132 kV
Date accepted
9 Feb 2020
Target energisation
31 Dec 2028
In a connection queue
Yes
Row last updated by the DNO
14 Nov 2024
Licence area
EPN
Address
Ipswich
Postcode
IP8 4JD

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.