Grid GuardianOpen the evidence in the app

Brunel Road

Brunel Road, Welsh Power Group Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 14 MW, grid supply point Tilbury.

Customer
Welsh Power Group Limited
Status
Connected
Capacity
14 MW
Maximum import capacity
0.6 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Tilbury
Bulk supply point
South Benfleet Grid 33kV
Point of connection
Thundersley Primary 11kV
Voltage
11 kV
Date connected
12 Feb 2021
In a connection queue
No
Row last updated by the DNO
17 May 2021
Licence area
EPN
Address
Benfleet
Postcode
SS7 4PS
Export MPAN
1050002061348/1050002061339
Import MPAN
1050002061320/1050002061310

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source