Grid GuardianOpen the evidence in the app

Brook Farm

Brook Farm, Connect2Grid, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 49.9 MW, grid supply point Bramford.

Customer
Connect2Grid
Status
Connected
Capacity
49.9 MW
Maximum import capacity
50 MW
Technology
Storage (Storage - Electrochemical (Batteries))
Flexible connection
No
Grid supply point
Bramford
Voltage
132 kV
Date connected
11 Aug 2022
In a connection queue
No
Row last updated by the DNO
14 Aug 2023
Licence area
EPN
Address
Flowton, Ipswich
Postcode
IP8 4LJ
Export MPAN
1097000000379
Import MPAN
1097000000360

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.

Source