British American Tobacco

British American Tobacco, British American Tobacco, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1.6 MW, grid supply point City Road.

Customer
British American Tobacco
Status
Connected
Capacity
1.6 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
City Road
Bulk supply point
Back Hill 33kV
Point of connection
Kingsway 11kV
Voltage
11 kV
Date connected
23 Sept 2018
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
London Power Networks plc
Address
Globe House, Temple
Postcode
WC2R 2PG
Export MPAN
1200010257778

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.