Bridge Farm

Bridge Farm, ASE UK Holding Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 30 MW, grid supply point Bramford.

Customer
ASE UK Holding Limited
Status
Accepted to connect
Capacity
30 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Bramford
Bulk supply point
Thetford 132/33kV
Point of connection
Stanton Primary 33/11kV
Voltage
33 kV
Date accepted
12 May 2025
In a connection queue
Yes
Row last updated by the DNO
15 Jan 2026
Licence area
EPN
Address
Stow Lane, Stowlangtoft
Postcode
IP31 3JU

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.