Bloomberg Building
Bloomberg Building, Bloomberg Building, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 2.4 MW, grid supply point City Road.
- Customer
- Bloomberg Building
- Status
- Connected
- Capacity
- 2.4 MW
- Technology
- Fossil - Oil (Engine (combustion / reciprocating))
- Flexible connection
- No
- Grid supply point
- City Road
- Bulk supply point
- Finsbury Mkt F 33kV
- Voltage
- 11 kV
- Date connected
- 27 Jul 2017
- In a connection queue
- No
- Row last updated by the DNO
- 14 Dec 2021
- Licence area
- London Power Networks plc
- Address
- 3 Queen Victoria Street, City Of London
- Postcode
- EC4N 4TQ
A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.
Source
- UK Power Networks Embedded Capacity Register (1 MW and over), UK Power Networks, publication of 14 Oct 2026. CC BY 4.0, UK Power Networks.