Bletchingley Central

Bletchingley Central, YLEM BESS (South) Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 1 MW, grid supply point Northfleet East.

Customer
YLEM BESS (South) Limited
Status
Accepted to connect
Capacity
1 MW
Technology
Gas (Engine (combustion / reciprocating))
Flexible connection
No
Grid supply point
Northfleet East
Bulk supply point
Dormansland Grid 33kV
Point of connection
Crowhurst 11kV
Voltage
11 kV
Date accepted
25 Jun 2019
Target energisation
10 Jan 2026
In a connection queue
Yes
Row last updated by the DNO
14 Jun 2024
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Eastbourne Road, Godstone
Postcode
RH9 8JB

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.